Energy · State-owned utility · Sep 2023 – Nov 2024
RPA and a dashboard system for a national power transmission grid
Delivered five UiPath robots across two contracts for a state-owned power transmission grid. Developed a data dashboard system integrating core business systems. Reduced maintenance planning time from 16 hours to 15 minutes. Delivered 18 dashboards with 100 indicators, exceeding the original requirement of 10 dashboards and 50 indicators.
- Client
- State-owned national power transmission grid operator, Mongolia (five regional branches)
- My role
- Engagement lead and solution designer (Co-founder & CEO | Process Transformation Lead, BPSolution) — team of 5
16 h → 15 min
Consolidating maintenance and investment plans across five branches
64–98%
Reduced processing time across all three automated processes
2 days → live
weekly operations-meeting preparation, now updated automatically
18 / 100
dashboards and indicators delivered, against 10 and 50 required
How data reaches the operations meeting
Before
Every week · two days of manual preparation
- 1
Data sits in separate systems — outages, inventory, HR and documents, tenders
- 2
Unreliable data: free-text entries, duplicate records and spelling errors
- 3
Each department prepares its own PowerPoint slides
- 4
Collecting and merging the slides takes two days
- 5
Meeting runs from the merged slide deck
After
Every night · updated automatically
- 1
APIs pull data from each system every night
- 2
Robots clean and fix records; standard names and options
- 3
18 dashboards with 100 indicators update automatically
- 4
Departments add only what no system holds, through data-entry forms
- 5
Meeting runs straight from the dashboard


- S
Situation
A state-owned company operated the national high-voltage transmission network through five regional branches. Critical reporting was largely manual.
- Maintenance and investment planning took 16 hours per cycle.
- Performance reporting took 3 hours.
- Headcount reports were rebuilt for every staffing order.
- VAT e-receipts were entered manually, one by one.
- Management data was scattered across operational systems and Power BI.
- Preparing weekly operations meeting presentations took two days.
- Data quality was poor: free-text entries, duplicate records, inconsistent names and spelling errors.
- T
Task
As BPSolution’s co-founder and CEO, win and lead two contracts:
- 2023: Automate three manual processes and establish a data management system.
- 2024: Clean operational data and deliver a dashboard system with at least 10 dashboards and 50 indicators within six months.
- A
Action
- Designed the solution architecture: Combined UiPath robots, a central data management system and Tableau, with architecture approval from the chief engineer and head of IT.
- Automated three processes: Branch-level maintenance and investment planning with performance reporting, headcount reporting, and VAT e-receipt issuance.
- Won the second contract: Secured a 2024 public tender to improve data quality and expand the dashboard system.
- Standardised operational data: Agreed naming conventions with business units, corrected records through APIs, standardised free-text weather entries and removed duplicates.
- Expanded automation: Developed two additional robots to extract HR and document data and clean records where APIs were unavailable, bringing the total to five robots.
- Built the dashboard platform: Delivered 18 dashboards with 100 indicators, including operational, maintenance, investment, inventory, HR and tender reporting. Added data-entry forms, self-service chart building and role-based access.
- Managed end-to-end delivery: Used WBS, RACI, progress reporting and a 32-item test report. Completed handover, documentation and user training.
- R
Result
- Maintenance and investment planning: Reduced from 16 hours to 15 minutes per cycle (98% faster).
- Performance reporting: Reduced from 3 hours to 17 minutes (91% faster).
- Headcount reporting: Reduced processing time by 75%, saving approximately 78 hours annually.
- VAT e-receipts: Reduced processing time by 64%, saving approximately 21 hours annually.
- Annual time savings: Approximately 178 hours across the three automated processes.
- Dashboard delivery: Delivered 18 dashboards and 100 indicators, exceeding the original requirements by 80% and 100%, respectively.
- Management reporting: Replaced two days of weekly PowerPoint preparation with eight automatically updated meeting dashboards.
- Data quality: Established standardised, dashboard-ready operational data using five robots.
- Contract delivery: Completed six days early, with 100% scope acceptance and no late penalties.